The ATESS HPS series consists of all-in-one hybrid inverters built for commercial and industrial installations, where uninterrupted power delivery matters just as much as conversion efficiency. Each unit integrates the inverter, transformer, and transfer switching gear into a single enclosure, removing the need for extra BoS components and simplifying on-site installation. The series' standout feature is its seamless switching between grid-tied and off-grid operation in under 10 ms, making it a strong fit for facilities that cannot tolerate power interruptions, such as data centers, manufacturing plants, or logistics hubs. HPS units also support parallel operation of up to 8 devices, allowing a single installation to scale up to 1200 kW of capacity without redesigning the system architecture. The inverters offer programmable working modes and remote control of a diesel generator (DG), enabling flexible management of hybrid energy sources, PV, battery, grid, and generator, based on tariffs and load demand. An intuitive touchscreen LCD simplifies configuration and monitoring without external tools. It's a solution built for integrators and investors seeking a reliable, scalable alternative to conventional UPS systems and grid-tied inverters.
Ranking
Specifications
Pros and cons
Transfer time below 10 ms between on-grid and off-grid operation practically eliminates power interruptions for critical loads, putting the HPS series in the same league as dedicated UPS systems rather than typical hybrid inverters.
Per ATESS's current datasheets (HPS100/120/150 models), the system scales to 8 inverters in parallel with up to 1200 kW total capacity, allowing installations to grow without changing the system architecture - older 2024 documentation still cited only 4 units and 600 kW.
Integrating the transformer and automatic transfer switch (ATS) into a single enclosure removes the need for external BoS components, cutting on-site installation time and reducing the number of service interfaces.
Programmable operating modes and remote generator control enable automatic energy cost optimization based on tariffs and load - a feature rarely available in commercial inverters of this power class.
A built-in touchscreen allows full configuration and monitoring without a laptop or extra software, shortening commissioning time for integrators.
ATESS's official materials are not fully consistent over time: 2024 documents cite 4 units/600 kW, a 2025 white paper mentions only 2 units, while the latest datasheets state 8 units/1200 kW. Buyers should confirm the current limit for the specific model before designing an installation.
ATESS was founded in 2017, giving it a shorter operating history than Tier-1 inverter makers (Huawei, SMA, Sungrow, with 15-20+ years in business), meaning less field data on long-term hardware durability.
Alternatives
About the HPS series
These answers cover the whole series. Where a figure differs, the specification above is this model's own.